A and B together can finish a job in 40 days. A can do the same job on her own in 60 days. How long will B take to do the three-fourth of the same work all alone?
Explanation:
Let the total work to be done = LCM(40, 60) = 120 units.
Efficiency of A alone = 120/60 = 2 units/day
Efficiency of A and B together = 120/40 = 3 units/day
∴ Efficiency of B alone = 3 - 2 = 1 unit/day
⇒ Time taken by B alone to complete the work = 120/1 = 120 days.
⇒ Time taken by B alone to complete 3/4th work = 120 × 3/4 = 90 days.
Alternately, Let B taken B days to complete the work alone.
⇒ 140 = 160 + 1B
⇒ 140 - 160 = 1B
⇒ 1B = 3-2120
⇒ B = 120
Hence, option (c).