A man, a woman, and a child can do a piece of work in 12 days. Man only can do it in 48 days. Woman can do it in 32 days and in how many days child can do the same work?
Explanation:
Let the amount of work to be done = LCM (12, 48, 32) = 96 units.
∴ Efficiency of a man = 96/48 = 2 units/day Efficiency of a woman = 96/32 = 3 units/day Let the efficiency of a boy = 'b' units/day
A man, a woman, and a child can do a piece of work in 12 days.
⇒ 96 = (2 + 3 + b) × 12 ⇒ 8 = 2 + 3 + b ⇒ b = 3
∴ Efficiency of a boy = 3 units/day
⇒ Time taken by a boy to complete the work alone = 96/3 = 32 days.
Alternately, Say the child takes C days to complete the work.
Amount of work all together can do in one day = 112 of total work.
Amount of work Man can do in one day = 148 of total work
Amount of work Woman can do in one day = 132 of total work
Amount of work Child can do in one day = 1C of total work.
According to question:
⇒ 148 + 132 + 1C = 112
⇒ 1C = 112- 148 - 132 = 132
⇒ C = 32 days.
Hence, option (c).