Discussion

Explanation:

Work done by 1st pipe in 1 hour = 1/18

Work done by 2nd pipe in 1 hour = 1/24

∴ Work done by both pipes in 1 hour = 18+124=772 1/18+1/24)=7/72

∴ Both pipes together can fill in 72/7 hrs i.e., 1027 hours

Hence, option (c).

» Your doubt will be displayed only after approval.


Doubts


Feedback

Help us build a Free and Comprehensive Preparation portal for various competitive exams by providing us your valuable feedback about Apti4All and how it can be improved.


© 2024 | All Rights Reserved | Apti4All