Explanation:

Let the efficiency of Amish be 2 units/day.

If she can do the entire work in 20 days.
⇒ Total work to be done = 2 × 20 = 40 units.

Now, she works with full efficiency for first 4 days and with half efficiency for another 12 days.
∴ Work done by Amisha = 2 × 4 + 1 × 12 = 20 units.

⇒ Amisha's co-worker completed the remaining (40 - 20 =) 20 units of work in the last 12 days.

Hence, to complete the entire 40 units of work the co-worker will take 24 days.

Hence, 24.