Discussion

Explanation:

Let the number of men initially be 'm'.

m men can complete the work in 20 days while (m - 10) men can complete the same work in 40 days.

∴ m × 20 = (m - 10) × 40

⇒ m = 2m - 20

⇒ m = 20

Hence, option (d) 

» Your doubt will be displayed only after approval.


Doubts


Feedback

Help us build a Free and Comprehensive Preparation portal for various competitive exams by providing us your valuable feedback about Apti4All and how it can be improved.


© 2023 | All Rights Reserved | Apti4All