Discussion

Explanation:

Assume, C can do x work in 1 day; B can do 2x work in 1 day; and A can do 4x work in 1 day. 

Total work = 12(x + 2x + 4x) = 84x

A and B work for 8 days, 8(2x + 4x) = 48x will be completed.

B and C can do 3x work in 1 day.

So, the remaining 36x can be completed in 12 days.

Hence, option (c).