Discussion

Explanation:

(A+B)’s 1 day’s work = 1/45 and A’s day’s work = 1/60

∴ B’s 1 day’s work = 1/45 - 1/60 = (4-3)/180 = 1/180

Hence, B alone will finish the work in 180 days

Alternately,

Let the total work to be done = LCM(45, 60) = 180 units

A can complete this work in 60 days, hence A’s efficiency = 180/60 = 3 units/day

A and B together can complete this work in 45 days, hence their combined efficiency = 180/45 = 4 units/day

∴ B’s efficiency = 5 – 4 = 1 unit/day

Time taken by B alone to complete the whole work = 180/1 = 180 days.

Hence, option (d).