Discussion

Explanation:

Suppose the original work would have been completed in d days.

Total work to be done = 30 × d

Work done in first 25 days = 30 × 25
Work done in next 12 days = 35 × 12

⇒ 30d = 30 × 25 + 35 × 12
⇒ 30d = 750 + 420
⇒ 30d = 1170
⇒ d = 39

∴ Had 5 more men not been employed the work would have got delayed by (39 – 38 =) 1 day.

Hence, option (a).