Let x men can complete the work in 160 days, whereas 
(x + 18) men can complete the work in 140 days.

⇒ x × 160 = (x + 18) × 140

⇒ 8x = 7(x + 18)

⇒ x = 7 × 18 = 126

Hence, option (d).