Explanation:

Assume C can do x work in 1 day,

B can do 2x work in 1 day, and

A can do 4x work in 1 day. 

Total work = 12(x + 2x + 4x) = 84x
 
Now, A and B work for 8 days, therefore 8(2x + 4x) = 48x of work will be completed. B and C can do 3x work in 1 day. 

So, the remaining 36x of work can be completed in 12 days.

A gets Rs. 2000 for his 32x of work. 

B has done 40x of work. 

So, B will get (2000 × 40)/32 = Rs. 2500.

Hence, option (b).