A, B, C together can finish a work in 20 days. A and C together can do thrice as much as B does. Also A and B can do twice as much as C does. Find the time taken by A to finish the work :
Explanation:
Let the time taken by them is A, B and C days respectively.
∴ 1A+1B+1C=120 …(1)
1A+1C=3B …(2)
1A+1B=2C …(3)
Adding 1/B both sides in (2) we get,
120=4B
⇒ B = 80 days.
Similarly, adding 1/C both sides in (3) we get,
120=3C
⇒ C = 60 days.
From (1) we get
1A+180+160=120
⇒ A = 48 days
Hence, option (b).