A alone would take 8 days more to complete the job than if both A and B worked together. If B worked alone, he took 4.5 days more to complete the job than A and B worked together. What time would they take if both A and B worked together?
Explanation:
Let the time A and B take while working together be ‘x’ days.
As per question 1x+8+1x+92=1x
or, x+25∕2x+8x+92=1x
2x2+252x = x2+252x+36
x2 = 36
⇒ x = 6 days
Remember: Solution for an equation of the form 1x+a + 1x+b = 1x
is x = a×b
Hence, option (a).