Rudra can do a piece of work in 9 days, Pratap in 247 days and Singh in 18 days. All begin to do it together but Rudra leaves after 1 day and Pratap 2 days before the completion of work. How long would the work last?
Explanation:
Rudra can do a piece of work in 9 days, Pratap in 187 days and Singh in 18 days.
Let the work be completed in ‘n’ days.
∴ Rudra works for 1 day, Pratap for (n – 2) days and Singh for n days.
∴ 19+(n-2)18/7+n18 = 1
⇒ 8n-1218 = 1
n = 308 days or 334 days
Hence, option (d).