X, Y and Z can together complete a piece of work in 20 days. If Y does half what X and Z together do in 1 day, in how many days can Y alone do the complete work?
Explanation:
Let the time taken by each of them be X, Y and Z respectively.
∴ 1X+1Y+1Z=120 …(1)
Also, Y does half the work done by X and Z in a day, hence
1Y=121X+1Z or
1X+1Z=2Y …(2)
From (1) and (2)
2Y+1Y=120
Y = 60 days
Hence, option (c).