Please submit your concern

Explanation:

Total man-hours spent on onsite work = 90 + 100 + 150 = 340

Sum of the estimated and actual effort for offshore design = 100 + 100 = 200

Estimated man-hours of offshore coding = 410

Actual man-hours of offshore testing = 300

Half of the man-hours of estimated offshore coding = 205

∴ Total man-hours spent on onsite work is more closer to actual man-hours of offshore testing.

Hence, option (c).