The total effort in man-hours spent onsite is nearest to which of the following?
Explanation:
Total man-hours spent on onsite work = 90 + 100 + 150 = 340
Sum of the estimated and actual effort for offshore design = 100 + 100 = 200
Estimated man-hours of offshore coding = 410
Actual man-hours of offshore testing = 300
Half of the man-hours of estimated offshore coding = 205
∴ Total man-hours spent on onsite work is more closer to actual man-hours of offshore testing.
Hence, option (c).