Explanation:

Let the number of days required to complete the job be n.

1 person works on day 1, 2 on day 2, 3 on day 3, …. n on day n.

Using Unitary Method:
Each person has the same efficiency = 1120

Work done on
Day 1 = 1×1120
Day 2 = 2×1120
...
Day n = n×1120

∴ Total Work = 1×1120 + 2×1120 + ... + n×1120

This is also equal to 1.

∴ 1120+2120+3120+..+n120 = 1

∑n = 120
⇒ n(n+1)2 = 120
⇒ n = 15

Hence, 15.