In how many activities plant in Chennai could meet at least 50% shortfall in the actual operational hours compared to planned operational hours of plant in Kanpur ?
Explanation:
For Activity 1, 50% shortfall of planned and actual in Kanpur is 25.
Excess in chennai is 25. Hence,we can count this activity.
For Activity 2, we don't have any shortfall.
For Activity 3, the 50% shortfall will be 50.
Excess in chennai is 28, Hence this can be discarded.
For Activities 4 and 5, we don't have any shortfall.
For Activity 6, the 50% shortfall will be 25.
Excess in Chennai is 78. Hence,we can count this activity.
Hence, option (b)