Explanation:

Let, the number of women who started the work is N,

∴ Total work to be done = N × 7 woman days.

Day 1: Number of women worked = N

Day 2:  Number of women worked = N - 11

Day 3: Number of women worked = N - 22 and so on till

Day 12: Number of women worked = N – 11 × 11 = 121

∴ Total work done = N + (N – 11) + (N – 22) + … + (N – 121) = 12N - 726 woman days.

⇒ 12N – 726 = 7N

⇒ N = 726/5 = 145.2 = 145 (nearest integer)

Hence, option (c).