The project duration, measured in terms of the number of months, is the time during which at least one employee worked in the project. Which of the following pairs of the projects had the same duration?
Explanation:
Project duration for
Project 1: jan to mar i.e., 3 months Project 2: feb to apr i.e., 3 months Project 3: apr to aug i.e., 5 months Project 4: jul to nov i.e., 5 months Project 5: sep to dec i.e., 4 months
Hence, option (d).