If the total working hours were 100, which of the following tasks will account for approximately 50 hours?
Explanation:
Using the data from the previous question.
Total amount of work = 800 + 340 = 1140
Total coding man-hours = 410 + 100 = 510
Total design man-hours = 90 + 100 = 190
Total offshore testing man-hours = 290
Total offshore testing plus design man-hours = 290 + 190 = 480
50% of 1140 = 570
510 is more closer to 570.
Hence, option (a).