A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is
Explanation:
Let the efficiency of each person be ‘e’ units/hour.
Given, 35% work is done by N men in 10 days working for 7 hours/day, while 65% work is done by N-10 men in 14 days working for 10 hours/day
⇒ N×10×70.35= (N-10)×14×100.65
⇒ N×77= (N-10)×1413
⇒ N = (N-10)×1413
⇒ 13N = 14N – 140
⇒ N = 140
Hence, option (b).